Major Milestones
- 9/9/08 – Official Group Formation
- 9/26/08 – Requirements Analysis
- 10/3/08 – Hull Design
- 10/8/08 – Proposal for Funding
- 10/15/08 – Component Ordered
- 11/1/08 – 2/13/09 – Develop \ Build
- 12/1/08 – 2/20/09 – Integrate
- 2/20/09 - Submerge
- 3/6/09 - Move
- 4/3/09 - Track Object
- 4/3/09 - Robotic Arm
- 4/3/09 - Hydrophone
- 4/22/09 – Senior Design Day
- 8/09 – AUVSI Competition
Click Here to open the PDF version of the Gantt Chart